Thursday 21 November 2024
 4.7°C   NE Fresh Breeze
Ocean Kinetics - The Engineering Experts

Council / Viking bond well worth waiting for – SIC chief executive

The Viking wind farm stood still for number of days earlier this month denote high winds. Photo: Shetland News

THE LONG-awaited and overdue financial bond for the Viking Energy wind farm has finally been signed, three and half years after it should have been in place.

The £40 million bond is a safety guarantee for the planning authority that sufficient funds are in place should owner SSE Renewables not be able to comply with its legal obligation to decommission and restore the wind farm site in Shetland’s central mainland.

The lack of a bond has been a bone of contention for a long time as planning conditions stipulate that construction of the £600 million wind farm should not have commenced before a bond was in place.

However, construction of the 103 turbine wind farm started in the summer of 2020 and is now in the final stages of completion. The development is due to become operational later this year.

An ‘irrevocable standby letter of credit’ by Banco Santander in favour of Shetland Islands Council and at the request of Viking Energy Wind Farm LLP for a maximum of £40 million was signed by all parties on Tuesday last week.

This translates to a value of around £90,000 per installed megawatt, which is higher than the typical values of decommissioning bonds for wind farms on the UK mainland.

When entering into negotiations with the council in 2019, SSE Renewables’ initially proposed a bond to the value of £11.2 million.

However, the council did not think this was sufficient and commissioned an evaluation to establish what a reasonable level would be.

SIC chief executive Maggie Sandison said she was “very satisfied” that the council had now managed to secure a much better deal in terms of value and type of bond.

She said the principle of putting a bond in place was agreed with the developer at a very early stage, and as such did not undermine the council’s negotiating position as was suggested by opponents of the project.

Become a member of Shetland News

 

The chief executive also said that the council had been advised by its solicitors that it could not have stopped construction work because a decommissioning bond is not regarded as “going to heart” of the development and SSE Renewables had also agreed to the principle of a bond. What was at dispute was the size and the type of bond.

SIC chief executive Maggie Sandison. Photo: Hans J Marter/Shetland News

“What we actually got is a very secure bond and a much higher level that was originally proposed, so I think the time take to negotiate this was worth doing.

“We have to remember that bond only ever kicks in at the end of life of the Viking wind farm and only if the company don’t decommission which is a legal requirement on them.

“So, this is something that wouldn’t be call upon for 30 years plus, and only as a second position after the developer wasn’t available to do the decommissioning themselves.

“The position that we secured is good, and better than it would have been had we rushed the condition in 2020, and we get the opportunity to revalue the decommission bond every couple of years.”

However, Frank Hay, the chairman of Sustainable Shetland, the group that has been opposing the wind farm development for the last 15 years, said he was less than impressed by what he had seen.

“It is very unsatisfactory to have a planning condition that was meant to be in place before work commenced only, potentially, being discharged when work is more or less complete,” he said.

“The negotiating position of the SIC must have been much weaker having already permitted work to commence.

“Why has this been stipulated? That could lead to a requirement to renegotiate the bond with a different provider.

“We would hope that the SIC have been provided with a detailed analysis of how the £40 million figure was arrived at. In previous correspondence with Viking/SSE the SIC were insisting on that.”

Councillor Ian Scott, a critic of the wind farm development, said it had been a big surprise when it emerged that a bond had not been put in place prior to construction start.

“How far £40 million pounds will go in 25 years is anybody’s guess, so I presume inflation has been built into the figure,” he said.

A letter confirming that the financial guarantee required under condition five of the original planning consent for the Viking wind farm is now in place, has been added to the council’s planning website here.

Sandison added that similar decommissioning bonds would be negotiated for the three other onshore wind farm projects that are due to be built in Shetland over coming years.

Become a member of Shetland News

Shetland News is asking its many readers to consider paying for membership to get additional features and services: -

  • Remove non-local ads;
  • Bookmark posts to read later;
  • Exclusive curated weekly newsletter;
  • Hide membership messages;
  • Comments open for discussion.

If you appreciate what we do and feel strongly about impartial local journalism, then please become a member of Shetland News by either making a single payment, or setting up a monthly, quarterly or yearly subscription.

 
Advertisement 
Advertisement 
Advertisement 
Advertisement 

Newsletters

Subscribe to a selection of different newsletters from Shetland News, varying from breaking news delivered on the minute, to a weekly round-up of the opinion posts. All delivered straight to your inbox.

Daily Briefing Newsletter Weekly Highlights Newsletter Opinion Newsletter Life in Shetland Newsletter

JavaScript Required

We're sorry, but Shetland News isn't fully functional without JavaScript enabled.
Head over to the help page for instructions on how to enable JavaScript on your browser.

Your Privacy

We use cookies on our site to improve your experience.
By using our service, you agree to our Privacy Policy and Cookie Policy.

Browser is out-of-date

Shetland News isn't fully functional with this version of .
Head over to the help page for instructions on updating your browser for more security, improved speed and the best overall experience on this site.

Interested in Notifications?

Get notifications from Shetland News for important and breaking news.
You can unsubscribe at any time.

Have you considered becoming a member of Shetland News?

If you appreciate what we do and feel strongly about impartial local journalism, then please consider paying for membership and get the following features and services: -

  • Remove non-local ads;
  • Bookmark posts to read later;
  • Exclusive curated weekly newsletter;
  • Hide membership messages;
  • Comments open for discussion.